PROline Prosonic Flow 93 PROFIBUS-DP/-PA 6 Commissioning
Endress+Hauser 81
6 Commissioning
6.1 Function check
Make sure that all final checks have been completed before you start up your measuring
point:
“Post-installation check” checklist Page 40
“Post-connection check” checklist Page 54
!
Note!
The technical function data of the PROFIBUS interface in accordance with
IEC 61158-2 (MBP) must be observed (FISCO model).
The bus voltage of 9 ... 32 V and the current consumption of 11 mA at the device can
be checked using a normal multimeter.
Using the LED on the I/O board (see Page 78), it is possible to carry out a simple
function check on the fieldbus communication in the non-hazardous area.
Switching on the measuring device
Once the function checks have been successfully completed, it is time to switch on the
supply voltage. The device is now operational.
The measuring device performs a number of self-tests after power-on. As this procedure
progresses the following sequence of messages appears on the local display:
Normal measuring mode commences as soon as start-up completes. Various measured
value and/or status variables appear on the display (HOME position).
!
Note!
If start-up fails, an error message indicating the cause is displayed.
PROSONIC FLOW 93
START-UP
RUNNING
Start-up message
▼
PROSONIC FLOW 93
SW AMPLIFIER
V XX.XX.XX
Display of current software
▼
PROFIBUS-DP/-PA
Display of installed input/output modules
▼
SYSTEM OK
OPERATION
Beginning of standard measuring mode
▼