Installation Instructions
Seite/Page 98 Kapitel/Chapter 6: Installation Instructions 30.10.12
3. Measure with a voltmeter (AC) the voltage between:
a) Generator housing and PMGi housing.
b) Generator housing and ground of the vehicle.
The measured voltage must be lower than 50 mV.
4. Test the installed protective devices (like RCD). If a RCD is installed, a functional test must be done. Check all
terminals for right connections. Measure all phases against each other and against the neutral wire.
5. If the generator is Protected by PME, make sure that all components has the same ground at the housing.
The protective devices must match the national regulation.
6.19 Set into operation
After the installation the generator must be brought in service. For this the „Service record and warranty registration
must be worked through and filled out by the installing technical trained person.
This document must be handed out to the owner. The owner must be instructed for the operation, maintenance and
hazards of the generator. These include the in the manual mentioned hazards and further ones, which are the result
of the specific installation and the connected components.
Note!:Send the original Service and warranty record to Fischer
Panda to get full warranty. Make a copy for your hands.