ATTENTION!
The external cooling water expansion tank may be filled only
up to the lower edge of the lower tension tape (see note "max")
in the maximum filling level in cold condition.
5.5.2 Ventilating at the first filling of the Internal Cooling Water Circuit
Fig. 5.5.2-1: Expansion ttank
Expansion Tank
1. Fill up the external cooling water expansion tank with coo-
lant.
ATTENTION: maximum fill level = „max.“- mark.
The cover of the external expansion tank temporarily must be
opend (all other closures are now closed!).
Fig. 5.5.2-2: Venting screw - Internal Cooling Water Pump
Venting Screws
2. Open venting screw on the pipe socket of the internal coo-
ling water pump. Close the vent screw when air free water
comes out
Check the water level in the expansion tank during the van-
ting. Fill up if necessary.
Never open the vent screw while the generator is running.
Sample picture
Fig. 5.5.2-3: Venting screw - Thermostat housing
3.Open vent screw on the thermostat housing. Close the vent
screw when air free water comes out
Check the water level in the expansion tank during the van-
ting. Fill up if necessary.
Never open the vent screw while the generator is running
Sample picture
4. Start the Generator
After filling the generator it must be started. During this first
phase of start-up, the generator may not be loaded. Switch
the generator off after about 10 sek. of operation!
5. Repeat the steps 1-4 till no air comes out of the vent screw
at tthermostat housing.