10-4 ALPS Advanced Line Protection System
GE Power Management
10.2 TEST CALCULATIONS 10 ALPS TEST PROGRAM
10
10.2.6 MT PHASE UNITS – ZONE 2
The following dialog box is displayed for this test. The values are the default values used when the user selects New Test
File from the File menu.
Figure 10–6: MT PHASE UNITS – ZONE 2 DIALOG BOX
10.2.7 M3 PHASE UNITS – ZONE 3
The following dialog box is displayed for this test. The values are the default values used when the user selects New Test
File from the File menu.
Figure 10–7: M3 PHASE UNITS – ZONE 3 DIALOG BOX