EasyManua.ls Logo

GE L90

GE L90
900 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
CHAPTER 5: SETTINGS CONTROL ELEMENTS
L90 LINE CURRENT DIFFERENTIAL SYSTEM – INSTRUCTION MANUAL 5-359
5
BRK 1 FLSHOVR SPV A to BRK 1 FLSHOVR SPV C — These settings specify FlexLogic operands (per breaker pole) that supervise
the operation of the element per phase. Supervision can be provided by operation of other protection elements, breaker
failure, and close and trip commands. A six-cycle time delay applies after the selected FlexLogic operand resets.
BRK FLSHOVR PKP DELAY — This setting specifies the time delay to operate after a pickup condition is detected.

Table of Contents

Related product manuals