GE
D
IRECTION FQ091019, REVISION 2 VIVID Q N SERVICE MANUAL
8-46 Section 8-3 - Internal Component Replacement Procedures
7.) Re-install the battery as described in the "Battery Installation Procedure" on page 8-5.
8.) Return the bearing handle as described in the "Bearing Handle Installation Procedure" on page 8-3.
9.) Turn ON the system and boot-up.
10.)Perform a complete functional check of the system, as described in Chapter 4 - General Procedures
and Functional Checks.
11.)Proceed to perform the following functionality tests:
- "SafeLock Cart - Grounding Continuity" on page 10-22 - only if the
Vivid q N system is currently mounted on the SafeLock cart
- "SafeLock Cart - Chassis Current Leakage Test" on page 10-24
- "Calibration Tests" on page 7-25
- "Full System Test" on page 7-10