13. Restart BMC when you installed a new server blade. See Restarting BMC
procedure on page 4-56.
14. Perform the Smart configure process. See Smart configure procedure for
server blade on page 4-52 section.
15. Verify that the replacement was successful through the MAR log. See
Alert information identification procedure on page 4-5 section.
16. Turn off LID LED for identifying the target blade. See Identify LED (LID)
on/off procedure on page 4-7 section.
Notice:
Do not install the server blade without the top cover. The server chassis
has a mechanical security to prevent installation without the top cover.
Bypassing this security feature can cause serious server chassis or server
blade damage.
Replacing an SMP connection board for CB 520X B1/B2/B3
Removing an SMP connection board
1. Put on an anti-static wrist strap.
2. Press a release latch on the SMP connection board.
3. Open a lever fully.
4. Pull out the SMP connection board straight forward.
Notice:
1. Do not release your hands from the lever until you put the SMP
connection board on an antistatic matt. If you release your hands, the
board may fall on the floor.
2. Do not pull out the SMP connection board at a tilt. Connectors in the
board may be damaged.
3. Do not touch the socket pins. The pins are physically sensitive.
5-8
Replacing parts
Hitachi Compute Blade 500 Series System Service Manual