7. If the GPU is installed on secondary cage, remove the secondary riser cage.
8. Remove the air baffle.
9. Install the Smart Storage Battery.
10. Route the battery cable as shown in below illustration.
11. Connect the controller backup power cable.
12. Install the air baffle.
13. If removed, install the secondary riser cage.
14. Install the access panel.
15. Install the server into the rack.
16. Connect all peripheral cables to the server.
17. Connect each power cord to the server.
Hardware options installation 81