Installing Panels
1. Reinstall the circuit breaker panel.
2. Secure filler panels to the rack rails on the rear door, as shown in Figure 3-95.
Install filler panels according to the U position markings on the cabinet. Ensure that filler panels fully
cover the rack rails.