EasyManuals Logo

Huawei FusionModule800 Installation Guide

Huawei FusionModule800
298 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #213 background imageLoading...
Page #213 background image
FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
4 Cable Routing
Copyright © Huawei Technologies Co., Ltd.
204
4.3 Power Cable Routing
Figure 4-15 Power cable routing
(1) Power cable from the battery to
the UPS
(2) Mains input power
cable
(3) PDU2000 power
cable
The customer can purchase power cables as required. The recommended specifications of mains input
power cables are as follows:
6 kW and 7.5 kW loads (BOM number: 25030857): 600 V/1000 V-ZA-YJV-5 x 16 mm
2
-Black (5
cores: yellow, green, red, blue, black)-107 A-CE
12 kW and 15 kW loads (BOM number: 25030858): 600 V/1000 V-ZA-YJV-5 x 25 mm
2
-Black (5
cores: yellow, green, red, blue, black)-138 A-CE
4.4 Smart Module Grounding
1. Deploy a general ground bar (shown by (1) in Figure 4-16) in the Converged Cabinet.
2. Connect the general ground point (shown by (1) in Figure 4-17) in each cabinet to the
general ground bar in the Converged Cabinet.
3. Connect the general ground bar in the Converged Cabinet to the floor ground bar or
collective ground bar.

Table of Contents

Other manuals for Huawei FusionModule800

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionModule800 and is the answer not in the manual?

Huawei FusionModule800 Specifications

General IconGeneral
BrandHuawei
ModelFusionModule800
CategoryStorage
LanguageEnglish

Related product manuals