FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
Copyright © Huawei Technologies Co., Ltd.
Figure 3-123 Securing a VCN540
----End
3.11.5 (Optional) Installing a LAN Switch
Context
The LAN switch needs to be installed in the 38 U position on the top of the IT cabinet front
side to the left of the Converged Cabinet, as shown in Figure 3-124.