IDS1000-A Air-Cooled Container Data Center
All-in-One Maintenance Guide
5 Parts Replacement
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
78
Figure 5-2 Detecting the voltages
Step 4 Hold down the faulty SPD module and pull it out, as shown in Figure 5-3.
Figure 5-3 Replacing an SPD module
If there is a faulty SPD module, it is recommended that all SPD modules be replaced.
If the SPD module cannot be pulled out, use a tool such as a flat-head screwdriver to lever it out.
Step 5 Install the spare SPD module, and switch on the SPD circuit breaker.
Step 6 Reinstall the protective panel.
----End
Follow-up Procedure
Dispose of the removed SPD module that is confirmed faulty.
5.1.4 Replacing a UPS5000-E Battery
Prerequisites
A UPS5000-E battery needs to be replaced.
A spare UPS5000-E battery of the same model is available and functional.