Verify component operation 157
Figure 107 Install a qualified SFP option into an DS2200 FC/iSCSI controller module
Verify component operation
View the CNC port Link Status/Link Activity LED on the controller canister face plate. A green LED indicates that
the port is connected and the link is up:
• For FC SFPs, see Figure 37 (page 45)or Figure 41 (page 49), and refer to table entry No.1
• For 10GbE iSCSI SFPs, see Figure 37 (page 45) or Figure 41 (page 49), and refer to table entry No.2
• For 1Gb iSCSI SFPs, see Figure 38 (page 46) or Figure 41 (page 49), and refer to table entry No.2
NOTE: To remove an external SFP connector, perform the installation steps in reverse order relative to what is
described in “Install an SFP transceiver” (page 156).
Canister face plate
Target CNC port
Installed SFP
(actuator closed)
Fiber-optic interface cable
Align SFP for installation
(plug removed/actuator open)