Lucent Technologies Galaxy Power System 4848/100
11 - 6  Maintenance and Replacement   Issue 5  June 2000
Replacement Procedures, continued
Installing or Replacing a Rectifier, continued
Step Action
11
Follow Steps 3-5 to install remaining rectifiers. Follow 
Steps 6-10 to set remaining ID numbers.
12
Verify that the system voltage reads 52.08V or desired float 
voltage.
13
Test replaced rectifiers using the “Testing Additional 
Alarms After Replacement of Rectifiers” procedure in this 
section.