Maintenance work on the carrier
7.13 Steering
7 - 96 3 302 744 en Maintenance manual
GMK5250L
09.03.2018
7.13.2 Pressure accumulator – checking the gas pressure
Pressure accumulators containing nitrogen (1)
have been built in for the steering of the 4
th
and 5
th
axle lines.
The filling pressure at 20 °C (68 °F) is 89 bar
(1,290 psi).
• Have the filling pressure checked, and if
necessary corrected, by
Manitowoc Crane
Care
or an authorised GROVE dealer or an
authorised specialist workshop.
G
Risk of accidents due to incorrect inspection.
The gas pressure test must be carried out only by an authorised official
inspector of pressure tanks or under his/her supervision or instructions.