EasyManuals Logo

Manitowoc Grove GMK 5250L Maintenance Manual

Manitowoc Grove GMK 5250L
354 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #223 background imageLoading...
Page #223 background image
Maintenance work on the carrier
7.20 Other maintenance work
09.03.2018
Maintenance manual 3 302 744 en 7 - 147
GMK5250L
7.20.6 Renewing the corrosion protection
Protective agent,
tools
– Spray gun with spray extension.
–Brush.
– Protective clothing, protective goggles.
Prerequisites – The undercarriage of the truck crane must be thoroughly cleaned.
– The truck crane must be raised on outriggers or parked over an inspection
pit.
– The engine must be switched off and secured against unauthorised use;
à p. 2 - 3.
Check the
following
At the factory, the underside of the carrier was sprayed with corrosion pro-
tection for the first time.
The corrosion protection is solvent-free and is water soluble while being
sprayed on. A transparent, waxy, protective film is formed after a drying
time of one hour.
• Check the condition of the original protective film.
• If required, remove any rust and touch up the paintwork before you spray
on a new protective film.
Processing
instructions
• Observe the processing instructions for corrosion protection:
– Processing temperature: above 10 °C (50 °F).
– Removability before drying: With water.
– Removability after drying: With solvent naphtha.
– Drying time: 1 hour.
s
M 12
Protective agent GROVE part no.
Corrosion protection 03140192

Table of Contents

Other manuals for Manitowoc Grove GMK 5250L

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK 5250L and is the answer not in the manual?

Manitowoc Grove GMK 5250L Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK 5250L
CategoryConstruction Equipment
LanguageEnglish

Related product manuals