SET-UP AND INSTALLATION RT9130E-2 OPERATOR MANUAL
4-30
Published 3-1-2018, Control # 559-03
5. Fold out deflection sheaves on all sections, refer to
Folding Out/In the Deflection Sheaves on the 8 m (26 ft)
Sections, page 4-32.
Removing 8 m (26 ft) Inserts
1. Sling the 8 m (26 ft) insert on an auxiliary crane and lift it
until the weight has been taken off the bearing points (2)
and (3) (Figure 4-20).
2. Remove the retaining clips and pins from the bearing
points (2) and (3) on both sides (Figure 4-20).
3. Insert the pins into the holders on the foot of the 8 m (26
ft) sections and secure them with retaining clips.

Table of Contents

Other manuals for Manitowoc Grove RT9130E-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove RT9130E-2 and is the answer not in the manual?

Manitowoc Grove RT9130E-2 Specifications

General IconGeneral
BrandManitowoc
ModelGrove RT9130E-2
CategoryConstruction Equipment
LanguageEnglish

Related product manuals