Fill / Vent Valve - continued
Testing
Meter Reading Required Action
anything other than OL Valve OK
OL Replace faulty valve
Meter Reading
(Acceptable Range)
Required Action
115V models*: 92.7 to 113.9
VDC
PC board is OK
Perform Continuity Test
230V models**: 186.5 to 228.4 VDC
* For input line voltages of: 104 - 127 VAC
** For input line voltages of: 207 - 253 VAC
Meter Reading Required Action
any reading out of the
acceptable range
Replace PC board
If you are testing the valve during a specific cycle mode
(Fill Mode, Vent Mode, etc), steps A thru C are not required.
Refer to Service Diagnostics section for steps A thru C.
Fill / Vent Valve: Supply Voltage Test
A) Activate the Service Diagnostics Mode.
B) Initiate the I/O Test.
C) Energize the desired valve (Fill or Vent).
D) Disconnect wires from valve terminals.
E) Set meter to ‘VDC’
F) Place meter probes wires.
Fill / Vent Valve: Continuity Test
A) Disconnect wires from desired valve.
B) Set meter to ‘M Ω’
C) Place meter probes on valve terminals.
Equipment Alert
Sterilizer door must be closed to perform fill valve test.