Confirming Warm-up Completion
When the power is turned ON in RUN or T Mode, the sub-display will flash W-UP to show that
the Sensor is warming up. Warm-up requires approximately 5 to 15 minutes. When warming
up has been completed, the normal display will be shown.
Measurement operations can be performed while in warm-up display status, but the precision of
measurements before warming up has been completed will be low. For high-precision measure-
ments, wait until warming up has been completed.