Replacing a ZS4-4 Battery
7.
Press the new battery into the battery holder with the positive (+) side facing the
metal tab that holds it in place.
8.
If you removed the PCIe card from slot 1, re-install it. See Replacing a ZS4-4 PCIe
Card.
9.
Replace the top cover on the chassis.
10.
Return the controller to the normal rack position by pushing the release tabs on
the side of each rail while slowly pushing the storage controller into the rack.
11.
Reconnect all cables to their original ports, referring to the labels previously
added as a guide. For cabling details, see the Oracle ZFS Storage Appliance
Cabling Guide.
12.
Connect the power cords to the power supplies.
13.
Verify that standby power is on, indicated by the Power/OK status indicator
flashing on the front panel about two minutes after the power cords are plugged
in.
Servicing the ZS4-4 Controller 73

Table of Contents

Other manuals for Oracle DE2-24

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oracle DE2-24 and is the answer not in the manual?

Oracle DE2-24 Specifications

General IconGeneral
BrandOracle
ModelDE2-24
CategoryStorage
LanguageEnglish

Related product manuals