6 Instructions for Assembly and Use – Standard Configuration
CB 160 Climbing Formwork
Introduction
Preparation
1. Assemble wall formwork.
2. Assemble platforms.
3. Assemble finishing platform.
To moving procedure:
Do not transport persons!
Do not transport any loose parts or
other loads!
Standard work flow
10. Place formwork on climbing plat-
form and secure.
11. Clean formwork and adjust if neces-
sary.
12. Reinforce second wall section.
13. Mount leading anchor and close
formwork.
14. Place formwork anchor.
15. Pour second wall section.
16. Remove advancing bolts and retract
formwork.
17. Mount scaffold mounting rings.
Initial use
1. Position wall formwork for first wall
section.
2. Add reinforcement to first wall
section.
3. Mount leading anchor and close form-
work.
4. Place formwork anchor.
5. Pour first wall section.
6. Remove advancing bolts and strike.
7. Mount scaffold mounting rings.
8. Attach climbing platforms.
9. Assemble tension anchor if necessary.

Other manuals for Peri CB 160