52 Instructions for Assembly and Use – Standard Configuration
CB 160 Climbing Formwork
C1 Planning and work preparation
Platform decking
The execution of the platform decking
must be carried out according to
DIN EN 12811.
All materials used must be of sufficient
quality, see Table 6.
Tripping hazards, unnecessary box
outs and openings in the decking are
to be avoided or covered.
The distance between the decking
and the structure should be max. 5 cm.
Gaps inbetween the planking must
not exceed 2 cm.
The spacing between the decking of
adjacent platforms must not exceed
2cm. Larger gaps are to be covered
with non-movable suitable materials
or safety nets (8.4) with a max. mesh
size of 2 cm are to be used.
Any openings in the decking, which
are required for normal working
procedures, must be covered with
non-movable suitable materials.
Safe working conditions for ties
are to be provided by intermediate
platforms.
(Fig. C1.02)
Minimum dimensions of plankings
see Table 2.
Permissible span of girders see Table 3.
Fig. C1.02
8.4
max. 5 cm