28
CB 240 Climbing Formwork
Instructions for Assembly and Use – Standard Configuration
B1 Work on the Construction Site
5.12
5.11
5.2
5
5.11
5.12
Anchoring
Assembly of the Leading Anchor
With Anchor Positioning Stud M24,
e.g. for TRIO Panel Formwork.
Initial Use and Standard Use
1. Fix Anchor Positioning Stud M24 (5.11)
to the marked position with nails
31x80 (4x) (5.12). (Fig. B1.06)
2. Tightly screw on pre-assembled Lea-
ding Anchor (5) on Anchor Positioning
Stud M24. (Fig. B1.07)
A more stable mounting is achieved
through the installation of the Anchor
Positioning Plate, see Assembly of
Advancing Bolt M24”.
In this case, the distances from the
holes to be drilled to the steel struts
of the formwork must be sufficient.
For safe positioning, firmly connect
the Threaded Anchor Plate (5.2) to the
reinforcement.
Check Assembly
height,
anchor spacings,
anchoring depth h,
alignment according to specifications,
turn over wire nails.
Checking the Leading Anchor and rein-
forcement measures can be done at the
same time.
Fig. B1.06
Fig. B1.07
Fig. B1.08