Mixing pump G 4 X smart Overview - Operation and service
Operation
30 2021-08-12
Transport of already running
machine
DANGER!
Risk of injury from discharged mortar!
Injuries to face and eyes can occur.
Therefore:
Before opening the couplings ensure that there is
no more pressure on the hoses (observe display
at mortar pressure gauge).
1. Carry out the following steps before beginning the transport:
2. First unplug the mains cable.
3. Unplug all other cable connections.
4. Remove water supply line.
5. Remove loose parts, e.g. compressor prior to transport by
crane.
6. Start transport.
24.5 Transport in individual parts
Fig. 29: Transport
1. Disassemble the machine in the units mixing tube and hopper
for easier transport. These can be transported separately.
25 Operation
25.1 Safety
Personal protective equipment
The following protective equipment has to be worn for all operative
work:
Protective clothing
Protective goggles
Protective gloves
Safety shoes
Hearing protection
NOTE!
Further protective equipment that is to be worn
when effective particular jobs will be pointed out
separately in the warning instructions of this
chapter.