T. 0.01 66
JUN 20th 1820
286002864 SINGLE
PEDESTAL ASSEMBLY
INSTRUCTIONS
21
6
1
17
7
2
15
5
13
12
3
21
16
10
21
21
[ ]120
4.72
[ ]120
4.72
[ ]54.8
2.16
[82]
3.23
[60]
2.36
[12]
.47
[ ]60.3
2.37
[ ]60.3
2.37
[ ]299.4
11.79
[ 6 ]19 .7
7.74
[98.4]
3.87
REAR OF PEDESTAL
FRONT OF PEDESTAL
CABLE
PASSAGE
PLAN VIEW
INSTALLATION INSTRUCTIONS:
1. Un-pack pedestal,
. Remove mounting hardware stretch wrapped to extrusion (item 3).2
. Remove V-Support back (item 5) secured by 2 M5-,8 X 25 (item 15).3 PHPMS SCREWS
. Remove front & rear base covers (items 6 & 7) secured by 4 M4-,7 X 16 screws (item 17).4 FHPMS ZN
. Position pedestal on the floor in the desired position and orientation. Please install the pedestal in a position far enough5 NOTE:
away from the ball rack to avoid potential damage caused by bowling balls falling from the ball rack.
6. Mark/transfer the mounting holes in base sheet metal - lower (item 1) to the floor.
Note if the standard mounting hole positions marked ‘A’ in the plan view below interfere with the cable conduit in the floor, use
both of the aternate positions marked ‘B’ in the plan view below for the supplied anchors.
. Remove base sheet metal - lower (item 1) from base sheet metal - upper (item 2) secured with 8 each of M5-,8 X 16 (item7 HHCS
12) & M8 D-127A (item 13).SWM ZN
. Position base sheet metal - lower (item 1) on the floor and install with the appropriate supplied anchors.8
For wood floors drill Ø 1/4 holes and secure using 4 or 5 each of 0.41 X 0.73 X 0.06 (item 21), 3/8 (itemFW ZN SWM ANSI ZN
21), and 3/8 X 2.00 (item 21).HHLB ZN
For concrete floors drill Ø 3/8 holes to a minimum depth of 3-1/2 inches [89mm], clear the holes of all debris and secure using 4
or 5 each of 0.41 X 0.73 X 0.06 (item 21), 3/8 (item 21) and 3/8 X 3.00 (item 21). Drive taperFW ZN SWM ANSI ZN ANCR TB ZN
bolt into place leaving 3/16 inch [4.8mm] head clearance. Tighten taper bolt to minimum of 40 - [54 N.m].FT LB
: extra flat washers 0.41 X 0.73 X 0.06 are included for leveling purposes; if not needed discard.NOTE FW ZN
. Install console cables thru the anti-short bushing (item 10) and thru the extrusion (item 3).9
. Re-install pedestal on base sheet metal - lower and secure with 8 each of M5-,8 X 16 (item 12) & M8 D-127A10 HHCS SWM ZN
(item 13).
. Re-install front & rear base covers (items 6 & 7); secure using 4 M4-.7 X 16 screws (item 17).11 FHPMS
. Install keyboard or assembly and connect per instructions provided with keyboard or .12 LCD LCD
. Re-install V-Support back (item 5); secure using 2 M5-.8 X 25 screws (item 15).13 PHPMS
Take care not to pinch any wires or cables.