24 MCS100FT · Operating Instructions · 8011893 V2-1 · © SICK AG
Preparations for Initial Start-up
Subject to change without notice
3.5 Preparing the electrical installation
Fig. 6 Electrical connections in the cover of the MCS100FT
1 Lay the signal lines.
2 Lay the tube bundle cable of the sampling probe.
3 Provide the mains supply voltage.
Power input
»Technical data«.
Plan suitable mains supply separation.
WARNING: Health risk by voltage
The preparation of the MCS100FT may only be performed by skilled electri-
cians who, based on their technical training and knowledge as well as
knowledge of the relevant regulations, can assess the tasks given and rec-
ognize the hazards involved.
The wiring system to the power source of the system must be installed and
fused according to the relevant regulations.
Do not connect any electrical signals to the MCS100FT.
Let SICK Customer Service connect the MCS100FT electrics.
Supply voltage connection.
M screw connection M32*8.5 D18-25
Duct for tube bundle cable
M screw connection M40*1.5 D22-32