Commissioning
63
Building Technologies A6V10257473_b_en_--.doc
Fire Safety & Security Products 01.2010
13.3 System test
1. check the extinguishing process by automatic and manual activation
2. check display of "Released" condition
3. check the pre-warning time
4. check sounders and warning panels operation
5. check RT-Alarm and RT-Fault
6. check fire controls operation
7. check the mechanical blocking device
8. check "Emergency hold/abort" and/or "Automatic blocked" functions
9. check display of "Loss of agent" condition by opening the corresponding
contacts
13.4 Commissioning validation
Commissioning is completed, when:
- all functions were checked and system works perfectly
- each detector was tested
- RT-Alarm and/or RT-fault works correctly
- no fault is displayed
- internal buzzer is not disabled (jumper X3 / XCM1002 = ON)
- permanent “Level 2” operating access is disabled (jumper X8 / XCM1002 =
OFF)
- all cylinders are connected and pressure or weight is correct
- mechanical blocking device is disabled
- all selector valves are closed (for multi-sector installation only)
- the responsible person in charge of the installation was trained and informed

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens XC10 Series and is the answer not in the manual?

Siemens XC10 Series Specifications

General IconGeneral
BrandSiemens
ModelXC10 Series
CategoryControl Unit
LanguageEnglish

Related product manuals