Table 11-1
Steps for restoring power to an appliance following a power
interruption
DescriptionActionStep
Initialize the hardware in the following order:
■ Storage systems
■ Master server
■ Media server
Note: Always turn on the storage shelf that is
furthest away from the main appliance first, then
move to the next closest shelf until you reach the
main appliance.
See the section called “Power restoration
procedures” on page 118.
For more information on the hardware initialization
process, see "Verifying the operation of the
appliance and storage hardware" in the Symantec
NetBackup 5230 Appliance Hardware Installation
Guide.
Initialize the storage systems
and appliance hardware.
Step 1
Once the appliance and attached storage systems
have initialized, verify the health status of all the
hardware components.
■ Run the Appliance Diagnostics Center from
the NetBackup Appliance Web Console, then
choose Perform a hardware health check.
See “Troubleshooting and tuning Appliance
from the Appliance Diagnostics Center”
on page 31.
■ Download the DataCollect log to check any
logs associated with the hardware.
See “Working with log files” on page 48.
Verify the status of the
hardware components.
Step 2
117Disaster Recovery
Disaster recovery scenarios