POWER REQUIREMENTS EM Server Bezel
Installation Manual June, 2011 2-13
POWER REQUIREMENTS The IPedge server should have a dedicated AC power circuit. The
specific input voltage and current requirements for each server is listed
the specifications for each model.
UPS
RECOMMENDATIONS
Toshiba recommends an uninterruptible power supply (UPS) with power
conditioning for the IPedge server. The recommended UPS from ONEAC
are shown in Table 2-3. The UPS shown in the table include power
conditionaing. If you already have a UPS in place Toshiba recommends
that you install the power conditioner listed in Table 2-3.
Table 2-3 IPedge System Power Conditioner and UPS
IPedge Server
EC EM
Power Conditioner PC180A-S2S PC360A-S4S
Battery
Backup
Time
30 Minutes ON700XAU-SN ON700XAU-SN
1 Hour ON700XAU-SN1 ON700XAU-SN1
2 Hours ON700XAU-SN1 ON700XAU-SN1
4 Hours ON700XAU-SN1 ON700XAU-SN2
8 Hours ON700XAU-SN2 ON700XAU-SN4