Appendix A: Forms and Check Sheets
The following forms and check sheets are included for use
with Trane start-up of CDHH CenTraVac™ chillers. Forms
and check sheets are used, as appropriate, for installation
completion verification before Trane start-up is scheduled,
and for reference during the Trane start-up.
Where the form or check sheet also exists outside of this
publication as standalone literature, the literature order
number is also listed.
CTV Form Installation Completion and Request for
Trane Service (CTV-ADF001*-EN)
CenTraVac Chiller Start-up Tasks to be Performed by
Trane
CenTraVac Chiller Annual Inspection List
CenTraVac Operator Log
Unit Start-up/Commissioning
Important: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane (or an
agent of Trane specifically authorized to
perform start-up) with notice of the scheduled
start-up at least two weeks prior to the
scheduled start-up.