116
CDHH-SVX003C-EN
Appendix B: Chiller Installation Completion and
Request for Trane Service
Important: A copy of this completed form must be
submitted to the Trane Service Agency that
will be responsible for the start-up of the
chiller. Start-up will NOT proceed unless
applicable items listed in this form have been
satisfactorily completed.
TO:
TRANE SERVICE OFFICE:
S.O. NUMBER:
SERIAL NUMBERS:
JOB/PROJECT NAME:
ADDRESS:
The following items
are being installed
and will be completed by:
Important: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane (or an
agent of Trane specifically authorized to
perform start-up) with notice of the scheduled
start-up at least two weeks prior to the
scheduled start-up. Equipment not started
by Trane is not warranted by Trane.
Notes: Improper installation of CenTraVac™ chillers,
including optional components, can result in start-
up delay and required rework. Follow all provided
instructions and in use particular care with optional
devices:
• Follow installation procedures for
RuptureGuard™; refer to CTV-SVX06*-EN for
CDHF, CDHG, CVHE, CVHF, CVHG, and
CVHM models, refer to CDHH-SVX003*-EN for
CDHH models, and refer to CVHH-SVX003*-
EN for CVHH CenTraVac™ chiller models.
• Do NOT over-insert or over-torque the probe of
the ifm efector™ flow detection controller and
sensor; refer to PART-SVN223*-EN or the
CenTraVac™ chiller Installation, Operation, and
Maintenance manual.
• Do NOT block serviceable parts when installing
isolation springs.
Expenses that result in improper installation of
CenTraVac™ chillers, including optional
components, will NOT be paid by Trane.
Check box if the task is complete or if the answer is “yes”.
1. Chiller
☐ In place and piped.
Note: Do not insulate the CenTraVac™ chiller or
adjacent piping prior to the chiller commissioning
by Trane service personnel. The contractor is
responsible for any foreign material left in the
unit.
2. Piping
Chilled water piping connected to:
☐ CenTraVac™ chiller
☐ Air handling units
☐ Pumps
☐ Optional ifm efector
®
flow detection controller and
sensor properly installed
Condenser and heat recovery condenser (as
applicable) piping connected to:
☐ CenTraVac™ chiller
☐ Pumps
☐ Cooling tower
☐ Heating loop (as applicable)
Additional piping:
☐ Make-up water connected to cooling tower
☐ Water supply connected to filling system
☐ Systems filled
☐ Pumps run, air bled from system
☐ Strainers cleaned
☐ Rupture disk or RuptureGuard™ ventilation piping
properly installed
☐ Optional RuptureGuard™ properly installed
3. Flow balancing valves installed
☐ Leaving chilled water
☐ Leaving condenser water
☐ Optional heat recovery or auxiliary condenser water
4. Gauges, thermometers, and air vents
☐ Installed on both sides of evaporator
☐ Installed on both sides of condenser and heat
recovery condenser (as applicable)
5. Wiring
☐ Compressor motor starter has been furnished by
Trane, or has been configured and installed in
compliance with the appropriate Trane Engineering
Specification for Starter by Others (available from
your local Trane Sales Office)
☐ Full power available
☐ Interconnecting wiring, starter to panel (as required)