CDHH-SVX003C-EN
117
External interlocks (flow switch, pumps auxiliary,
etc.)
Chiller motor connection (remote starters)
Note: Do not make final remote starter-to
compressor motor connections until
requested to do so by the Trane service
representative!
Chilled water pump (connected and tested)
Condenser water pump (connected and tested)
Optional ifm efector
®
flow detection controller and
sensor cable properly installed and secured for
non-stress at probe connector
Cooling tower fan rotation checked
Heat recovery condenser water pump (as
applicable)
115 Vac power available for service tools
All controls installed and connected
For CVHM chillers, indicate type of power
distribution grounding:
All magnetic starters installed and connected
6. Testing
Dry nitrogen available for pressure testing (for
disassembled units)
Material and equipment available for leak testing (if
necessary)
7. Refrigerant
For CDHH and CVHH chillers: Verify supplied
refrigerant is “Solstice ZD” Refrigeration Grade by
checking certificates provided with tanks.
Refrigerant on job site and in close proximity to
chiller
Total amount in cylinders/drums: ___________
(specify lb or kg) and fill in specifics below:
Number of cylinders/drums _____ of size _____
(specify lb or kg)
Number of cylinders/drums _____ of size _____
(specify lb or kg)
Note: After commissioning is complete, it is the
installer’s responsibility to transport empty
refrigerant containers to an easily accessible
point of loading to facilitate container return
or recycling.
8. System
Systems can be operated under load conditions.
9. Availability
Electrical, control personnel, and contractor’s
representative are available to evacuate, charge,
and test the CenTraVac™ chiller under
serviceman’s supervision.
10. Equipment room
Does the equipment room have a refrigerant
monitor/sensor capable of monitoring and alarming
within the allowable exposure level of the
refrigerant?
Does the installation have properly placed and
operating audible and visual refrigerant alarms?
Does the equipment room have proper mechanical
ventilation?
If it is required by local code, is a self-contained
breathing apparatus available?
11. Owner awareness
Has the owner been fully instructed on the proper
use and handling of refrigerant?
Does the owner have a copy of the MSDS for
refrigerant?
Note: Additional time required to properly complete the
start-up and commissioning, due to any
incompleteness of the installation, will be invoiced at
prevailing rates.
This is to certify that the Trane equipment has been
properly and completely installed, and that the applicable
items listed above have been satisfactorily completed.
Checklist Completed by
(Print Name):
SIGNATURE:
DATE:
In accordance with your quotation and our purchase order
number ______________, we therefore require the
presence of Trane service on this site, for the purpose of
start-up and commissioning, by ______________ (date).
Note: Minimum of two week advance notification is
required to allow for scheduling of the chiller start-up.
ADDITIONAL COMMENTS/INSTRUCTIONS
Appendix B: Chiller Installation Completion and Request for Trane Service