January 2016
2-41
WorkCentre WorkCentre 4150/4250/4260WorkCentre 4150/4250/42604150/
06-100, 200
Status Indicator RAPs
06-100, 200 LSU Error RAP
06-100 The machine has detected that the LSU did not reach a ready state within the correct
time.
06-200 The machine did not detect the laser beam within the correct time.
Procedure
WARNING
Switch off the electricity to the machine. Disconnect the power cord from the customer
supply while performing tasks that do not need electricity. Electricity can cause death or
injury. Moving parts can cause injury.
WARNING
Avoid exposure to laser beam. Invisible laser radiation.
Go to the relevant procedure:
4150 Checkout
4250 Checkout
4260 Checkout
4265 Checkout
4150 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 3. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 codes 06-100 and 06-110. Check that the LSU motor is up to the required
speed.
3. Check the wiring between the LSU and CN5 on the Main PWB.
4. If necessary, install a new LSU, PL 6.10 Item 1.
5. Perform the OF5 Main PWB Check RAP.
4250 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 32. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 codes 06-100 and 06-110. Check that the LSU motor is up to the required
speed.
3. Check the wiring between the LSU and CN39 on the Main PWB.
4. If necessary, install a new LSU, PL 6.10 Item 1.
5. Perform the OF5 Main PWB Check RAP.
4260 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 21. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 codes 06-100 and 06-110. Check that the LSU motor is up to the required
speed.
3. Check the wiring between the LSU and CN4 on the Main PWB.
4. If necessary, install a new LSU, PL 6.10 Item 1.
5. Perform the OF5 Main PWB Check RAP.
4265 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 37. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 codes 06-100 and 06-110. Check that the LSU motor is up to the required
speed.
3. Check the wiring between the LSU and CN9 on the Main PWB.
4. If necessary, install a new LSU, PL 6.10 Item 1.
5. Perform the OF5 Main PWB Check RAP.