2.2 Mechanical Installation
YASKAWA ELECTRIC EZZ010928 FSDrive-MV1000 Instructions 41
◆ Side-by-Side Installation
“Side-by-side” installation means a configuration in which a transformer panel, Power Cell panel and control panel
delivered as separate units are installed within one panel or by wiring between panels.
The following models are installed side by side in a block construction (Table 2. 7).
2-kV class: 700 to 2750 HP
4-kV class: 1250 to 5000 HP
Note: Models other than those indicated above are delivered with the transformer panel, Power Cell panel and control panel integrated
within a single frame.
On these models, eight holes are provided each on the transformer panel frame and Power Cell panel frame (refer to the
figure below).
Use M10
× 30L bolts, washers, S-washers, and nuts to join the sections.
Figure 2.8
Figure 2.8 Mounting Holes for Side-by-Side Installation (Drive: 2-kV Class, 700 HP)
Figure 2.9
Figure 2.9 Mounting Holes for Side-by-Side Installation (Drive: 4-kV Class, 1250 HP)
When installing side by side a drive in a block construction, ensure that the specifications indicated in the table below are
satisfied.
Table 2.8 Side-by-Side Configuration
Category Specifications
Bolts between Panel Tightening torque of M10 bolts provided as accessories: 18 to 23 Nxm (lb.in.)
Wiring between
Panel
Perform the following wiring between panels.
• Main circuit wiring
• Grounding bus bars
• Cooling fan wiring
Transformer panel frame
Arrows: Positions of bolts
Power Cell panel frame
Transformer panel frame
Arrows: Positions of bolts
Power Cell panel frame