9. Install the top covers on the instrument.
Prime the Fluid System 4.10
Please note that it may take from several minutes to more than an hour to initially stabilize the probes when setting up for
the first time.
To prime the fluid system:
1. From the Service screen, touch the [Pumps] tab.
2. Touch the button under B1 Pump to turn it on.
3. The instrument will prime the B1 buffer solution.
4. Once buffer flows from the end of the sipper, touch the button under B1 Pump to stop the pump.
5. Repeat this procedure to prime all other buffer bottles and calibrator bottles you have installed.
Prime all installed calibrator bottles daily to remove air bubbles from the tubing.