NoteAction
xx2000001593
Remove the tubular covers.2
Loosening the process hub
NoteAction
DANGER
Make sure that all supplies for electrical power,
hydraulic pressure, and air pressure are turned
off.
1
xx2000001538
Remove the screws and carefully open the cover.
CAUTION
There is cabling attached to the cover. The cover
cannot be removed completely.
2
Loosening the cables in the tubular
NoteAction
DANGER
Make sure that all supplies for electrical power,
hydraulic pressure, and air pressure are turned
off.
1
xx2100001483
Cut the cable strap.2
Continues on next page
544 Product manual - CRB 1300
3HAC083111-001 Revision: B
© Copyright 2022-2023 ABB. All rights reserved.
5 Repair
5.6.6 Replacing the axis-6 motor
Continued