EasyManua.ls Logo

ABB RER670 - Interlocking for Double CB Bay DB; Application

ABB RER670
506 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Section 1 Section 2
A1A2_DC(BS)
B1B2_DC(BS)
BB_ESBB_ES
BH_LINE
(WA1)A1
(WA2)B1 B2
A2
en04000512.vsd
BH_LINE
IEC04000512 V1 EN-US
Figure 120: Busbars divided by bus-section disconnectors (circuit breakers)
The project-specific logic are the same as for the logic for the double busbar
configuration described in section “Signals in single breaker arrangement”.
Signal
BB_DC_OP All disconnectors on this part of the busbar are open.
VP_BB_DC The switch status of all disconnectors on this part of the busbar is valid.
EXDU_BB No transmission error from any bay that contains the above information.
12.4.8 Interlocking for double CB bay DB
IP14167-1 v2
12.4.8.1 Application
M13585-3 v10
The interlocking for a double busbar double circuit breaker bay including
DB_BUS_A, DB_BUS_B and DB_LINE functions are used for a line connected to
a double busbar arrangement according to figure 121.
1MRK 506 375-UEN A Section 12
Control
Railway application RER670 2.2 IEC 285
Application manual