65
Installing an Avaya MCC1 Media Gateway
October 2002
Perform these tasks before you begin the installation:
• ‘‘Unpack and Inspect Media Gateway’’ on page 65
• ‘‘Unpack and Inspect Auxiliary Cabinet’’ on page 66
• ‘‘Unpack and Inspect Stratum 3 Clock Cabinet’’ on page 129
• ‘‘Check Circuit Packs’’ on page 66
• ‘‘Correct Shipping Errors’’ on page 67
Perform these tasks to install the media gateways:
• ‘‘Position the Media Gateway’’ on page 67
• ‘‘Position the Auxiliary Cabinet (Optional)’’ on page 67 and ‘‘Install Auxiliary Cabinet
Equipment’’ on page 68
• ‘‘Install Earthquake Protection for Media Gateway’’ on page 68, if required
!
WARNING:
If the approved ground or approved floor ground can only be accessed inside a dedicated
power equipment room, then connections to this ground should be made by a licensed
electrician. See Approved Grounds
. for more information.
• ‘‘Connect AC Power and Ground’’ on page 71 or ‘‘Connect DC Power and Ground’’ on
page 81
• ‘‘Connect Remote Power Off Cable’’ on page 90
• ‘‘Connect External Alarm Cable’’ on page 93
• Interconnect cabling between port networks
— Direct connect to rack hardware
— Direct connect to each port network (duplex and high/critical)
— Switch-connect to port networks (duplex and high/critical)
1 Check the customer’s order and the shipping packing lists to confirm all equipment is
present.
2 Check the S8700 Multi-Connect configuration adjuncts for damage and report all
damage according to local shipping instructions.
3 If any equipment is missing, report the information to your Avaya representative.
Unpack and Inspect Media Gateway
!
CAUTION:
A media gateway may weigh as much as 800 lb. (363 kg) and may be top heavy. Use
extreme caution.