13 PREINSTALLATION
CHECKLISTS
13.1 Floor Boxes
Checklist
Yes No n/a 1 Floor Boxes Comments Scheduled
1.1 Marking recess on the floor.
1.2 Digging the recess.
1.3
Bottom surface of recess must be
leveled no deeper than 33 cm.
1.4 Align and level the floor boxes.
1.5
Fix the floor boxes to the ground.
Brainlab does not provide the an-
chors.
1.6
Install conduits (minimum 100 mm
inner diameter
, preferably rigid
PVC tubes) from the floor boxes
to the cable through the bunker
rear wall --> to the generator
.
1.7 Concrete pouring.
1.8 Finished floor.
1.9
Storage of floor box aluminium
covers and all included items
within the floor box until final in-
stallation.
The final covers and all in-
cluded items within the floor
box are placed during system
installation.
They must be kept in a safe
place until installed by the
Brainlab team.
PREINSTALLATION CHECKLISTS
Site Planning Manual Rev. 1.0 ExacTrac Ver. 6.x 121