16 MEASURES TO BE TAKEN AT THE END OF THE WORKING DAY
1. Retract the telescopic boom fully.
2. Check that the platform is perpendicular to the boom.
3. Lower the boom/platform onto the support on the tow-bar.
- the limit switch on the transport support prevents the operation of the support
outriggers if the platform is not down
4. Close the cover of the platform control centre.
5. Turn the selector switch to position 0, and turn off the main switch.
6. If you want to recharge the battery, leave the mains cable connected; otherwise
disconnect the lift from the mains supply.
7. Make sure that the covers are locked.