20.2 DAILY INSPECTION (START-UP INSPECTION)
To be always performed at a new worksite and in the beginning of every
work day.
The user of the lift shall performed this inspection.
During inspection, attention shall be paid to the following issues:
- establishing the load-bearing capacity of the ground at the lifting site (see the
indicative table “Maximum permissible ground pressure for different soil materials”)
- verification of the lift's standing stability
- controlling the due operation of the position indicator
- testing of the emergency stop system's operation both from the platform and the
chassis control centres.
- testing the emergency descent system's operation both from the platform and the
chassis control centres
- testing the alarm signal
- checking the warning and signal lights
- checking the operation and cleanliness of the lights and reflectors
- checking the condition of the operating controls and testing of all work movements
- checking the condition of the access routes, the platform gate and the handrails
- checking the operation of the load limit switches (refer to the service instructions).
- checking the limit switches preventing the operation of the boom movements (refer
to the service instructions)
- checking the limit switches preventing the operation of the boom movements (refer
to the service instructions)
- checking the hydraulic system for tightness
- testing of the brakes
- checking the structures visually
- observe the location of nearby power lines (for safe distance see “General safety
regulations”)