Parallel System Installation Checklist

Each cabinet in the UPS system must be placed in a proper location for installation. Do not place the UPS under the
air outlet of the air conditioner.

All conduits and cables must be properly routed to the UPS.

All power cables shall be in proper size and connected to the correct terminals.

The neutral line has been installed between cabinets as required.

The ground wire shall be properly installed.

The parallel wiring shall be correctly installed between the UPS units.

The parallel wiring shall be correctly installed.

Fireproof mud shall be lled into gaps between the cables and the cabinet.

There is adequate workspace around the UPS and other cabinets.

The startup and operational inspection of the parallel system or accessory case shall be performed by Eaton customer
service engineers.

The positive, negative and neutral wires of the battery shall be installed correctly and properly.

The external battery switch is turned off.

An alarm label has been attached to the external battery switch
.