17
Copyright © 2022 Eaton Corporation plc. All rights reserved.
Chapter 3 UPS INSTALLATION PLAN
Install the UPS system in accordance with the following order:
1. Draft an installation plan for the UPS system (
Chapter 3
)
2. Select an installation site for the UPS system (
Chapter 3
)
3. Inspect and open the UPS cabinet (
Chapter 4
)
4. Unload and install the UPS cabinet, then install system circuits (
Chapter 4
)
5. Install any accessories or optional parts if needed (
Chapter 4
)
6. Fill out the installation checklist (
Chapter 10
Installation Checklist).
7. Eaton customer service engineers will carry out preliminary operational inspections and startup.
NOTE
Commissioning must be carried out by the customer service engineers of Eaton, otherwise, the warranty
provisions in
Chapter 9
will become invalid. Provision of this service is part of the sales contract on
the UPS. Please contact us in advance (it is usually required to notice three working days in advance) to
make an appointment for an ideal startup date.
CAUTION
Make sure that the line input supply is disconnected from the UPS during installation.
.
WARNING
The installation shall be carried out by qualified technicians in accordance with the applicable safety standard.
The UPS is not applicable to IT distribution system.
3.1. Creating an Installation Plan
Before installing the UPS system, please read carefully and understand all information about system
components to be installed in this manual. Formulate a reasonable installation plan based on the relevant
procedures and gures in Section
3.2 and the content of
Chapter 4
.