3.4 Post-installation check
Perform the following checks after installing the measuring device in the pipe:
Device condition/specifications Notes
Is the device damaged (visual inspection)? –
Does the device correspond to specifications at the measuring point, including
process temperature and pressure, ambient temperature, minimum fluid
conductivity, measuring range, etc.?
ä 141
Installation Notes
Does the arrow on the sensor nameplate match the direction of flow through the
pipe?
–
Is the position of the measuring electrode plane correct? ä 15
Is the position of the empty pipe detection electrode correct? ä 15
Were all screws tightened to the specified tightening torques when the sensor was
installed?
ä 23
Were the correct seals installed (type, material, installation)? ä 22
Are the measuring point number and labeling correct (visual inspection)? –
Process environment / process conditions Notes
Are the inlet and outlet runs respected? Inlet run 5 × DN
Outlet run 2 × DN
Is the measuring device protected against moisture and direct sunlight? –
Is the sensor adequately protected against vibration (attachment, support)? Acceleration up to 2 g by
analogy with IEC 600 68-2-6
ä 145