"Setup" menu → Advanced setup → Sensor adjustment
‣
Sensor adjustment
Installation direction
→ 144
‣
Zero point adjustment
→ 144
Parameter overview with brief description
Parameter Description Selection Factory setting
Installation direction Set sign of flow direction to match the
direction of the arrow on the sensor.
• Flow in arrow direction
• Flow against arrow direction
Flow in arrow direction
Zero point adjustment
All measuring devices are calibrated in accordance with state-of-the-art technology.
Calibration takes place under reference conditions→ 232. Therefore, a zero point
adjustment in the field is generally not required.
Experience shows that zero point adjustment is advisable only in special cases:
• To achieve maximum measuring accuracy even with low flow rates.
• Under extreme process or operating conditions (e.g. very high process temperatures or
very high-viscosity fluids).
Navigation
"Setup" menu → Advanced setup → Sensor adjustment → Zero point adjustment
‣
Zero point adjustment
Zero point adjustment control
→ 144
Progress
→ 144
Parameter overview with brief description
Parameter Description Selection / User interface Factory setting
Zero point adjustment control Start zero point adjustment. • Cancel
• Busy
• Zero point adjust failure
• Start
Cancel
Progress Shows the progress of the process. 0 to 100 % –
10.6.4 Configuring the totalizer