Transport platform SEP Serie
SEP user’s manual Page 14 of 89 Doc no. RD-7243-MA-001-02
4. Technical data
4.1. General data
Nominal speed (vertical travel)
0-40 ft/min (0-12,2 m/min)
Speed governor activation speed (centrifugal
brake)
MAXIMUM number of persons on the platform
13 persons (Equally distributed)
Single rack
(13090104)
26" x 26" x 5'-0"
(650 mm x 650 mm x 1,5 m)
Double rack
(13090137)
26" x 26" x 5'-0"
(650 mm x 650 mm x 1,5 m)
* MAXIMUM freestanding installation height
(without anchor)
* With adjustable legs: Prohibited!
MAXIMUM installation height (anchored)
** MAXIMUM first anchor installation height
** With adjustable leg 20 ft (6,0 m)
MAXIMUM height over the last anchor (highest
anchor)
During operation: 0 ft (0 m) MAX from the platform floor to the
last anchor.
During installation: 0 ft (0 m) MAX from the top of the
protection roof to the last anchor (highest anchor).
*** "Typical" spacing between anchors
*** 30 ft (9,0 m)
MIN 20 ft (6,0 m)
MAX 40 ft (12,0 m)
Spacing between cable guides
Pay load MAXIMUM (Capacity)
Important! Deduce the average load of workers
and their personal equipment.
∞ SEE SECTION OPERATION SAFETY INSTRUCTIONS,
ON PAGE 41.
Depending on model
5 000 lb (2 270 kg)
6 000 lb (2 720 kg)
7 000 lb (3 175 kg)
8 000 lb (3 630 kg)
MAXIMUM load during installation, assembly and
disassembly.
Do not operate below -4°F (-20°C).
Note: it is recommended to use the permanent heating system if
the platform is used in a [41°F (5°C) à -4°F (-20°C)] environment
REFER TO SECTION 5.5 ELECTRICAL CONNECTION (ON SITE), ON
PAGE 37.
MAXIMUM dynamic speed of the wind
During installation (assembly/disassembly)
Refer to local regulation in effect
Electrical characteristics
Specific to each unit
(See identification pate and engineering package specific to the
project for electrical data)
∞ SEE SECTION 12.1 ELECTRICAL TECHNICAL DATA, ON PAGE 79.
Table 2 – General data
* Base with adjustable jack legs: freestanding use/installation is forbidden at all time. The mast must be supported with
a crane or an independent lifting system for the installation of the first two (2) anchors.
** Base with adjustable jack legs: the first anchor must be put in place within the 20'-0" (6m) from the ground. Install the
subsequent anchors at "typical" spacing from one another. See « *** » bellow.
*** The typical spacing between anchors is 30'-0" (9 m) ± 10'-0" (3 m), however it is forbidden to install two (2)
subsequent anchors with more than a 10'-0" (3 m) difference compared to the two next/previous anchors set.
Valid example: (anchors 1-2 = distance of 25'-0" (7,5 m) and anchors 2-3 = distance of 35'-0" (10,5 m)).
Invalid example :(anchors 1-2 = distance of 25'-0" (7,5 m) and anchors 2-3 = distance of 40'-0" (12 m)).