Indoor unit connection check
Address setting
Refrigerant piping connection
(Outdoor unit)
Leak pressure test
Pressurize system with 609 psi (4.2 MPa) nitrogen
System must hold 600 psi for a minimum of 24
hours.
Vacuum evacuation and drying
Do not purge system with refrigerant.
Use a vacuum pump with check valve to prevent the
back flow of vacuum pump oil into the refrigerant
system.
Additional refrigerant charge
Calculate additional refrigerant charge. Add additional re-
frigerant with R410A gage manifold and hose.
Gas leakage check
Outside panel installation
Test run and adjustment
End of work
Hand over
Customer training