LPS-O Line Protection System GE Power Management
5.5 END OF TEST WITH FACTORY SETTINGS 5 FUNCTIONAL TESTS (FACTORY SETTINGS)
5
5.5 END OF TEST WITH FACTORY SETTINGS 5.5.1 ENDING TESTS
Make sure that the relay is no longer in test mode; select
END TEST MODE
from the test mode menu. Print
out or scroll through all of the settings. Compare them with the initial settings of the relay, and change to initial
values. If the initial settings were saved to a disk file with LPSO-Link before testing, download the file to the
relay.