Operation GEDA
®
MINI 60 S / MAXI 120 S / MAXI 150 S
Assembly and Operating Manual 60 / 90 BL068 GB Edition 03/2015
6.1.1 Checks before starting work
Check at least once a day for externally recognisable damage and de-
fects. - Report any changes or malfunctions detected immediately to the
company management or its authorised representative. If necessary,
shutdown and secure the scaffolding lift immediately.
Carry out a test run and check that the complete travel path is clear.
The scaffolding lift must immediately stop when
The EMERGENCY STOP button is pressed.
The overload equipment is activated.
The slack rope switch has switched off.
Checking the limit switch, refer to Chapter 5.5
During the test run, check the wire rope for signs of damage and
wear.
Check the mains supply cable and control lines for signs of damage

Table of Contents