5.5 Check after assembly and before each operation
• Check to ensure that
o The specified maintenance work and inspection procedures have
been carried out.
o The supply cable has an adequate cross section.
o No grease escapes at the gearbox.
o The length of rope is sufficient for the assembly height.
o Notices are present and legible (refer to Chapter 11)
o The danger zone at the lower loading point is cordoned off and in-
dicated.
o Fall protection at the upper load positions is installed in accord-
ance with the national regulations.
• Carry out a test run without load and check to ensure that
o The motor rotation direction agrees with the UP and DOWN but-
tons of the control points and that the EMERGENCY STOP button
interrupts travel.
o The wire rope indicates no damage.
o The flexible drum guard switches off when the rope is slack.
o The wire rope is correctly wound onto the rope drum.
• Carry out a test run with load (refer to the load capacity) and check
to ensure that
o The motor brake correctly functions.
o If the load capacity is exceeded (raising the winch) and the rope
weight is moved against the pivot arm, the UP motion is switched
off.